ITIL® Foundation – Exam Test – Q167

Which of the following availability management activities is/are considered to be proactive as opposed to reactive?
1. Monitoring system availability
2. Designing availability into a proposed solution

A. None of the above
B. Both of the above
C. 1 only
D. 2 only

D. 2 only