ITIL Foundation V4 exam practice – Question150

What is a change schedule PRIMARILY used for?


A.
To help plan, authorize and schedule emergency changes
B. To publish a list of service requests that users can select
C. To ensure that a single change authority reviews every change
D. To help plan changes, assist in communication and avoid conflicts

Correct Answer: D