ITIL® Foundation – Exam Test – Q202

Which of the following are benefits to the business of implementing service transition?
1. Better reuse and sharing of assets across projects and resources
2. Reduced cost to design new services
3. Result in higher volume of successful changes

A. 1 and 2 only
B. 2 and 3 only
C. 1 and 3 only
D. None of the above

C. 1 and 3 only

ITIL® Foundation – Exam Test – Q201

A Service design package (SDP) would normally be produced for which of the following?
1. A new IT service
2. A major change to an IT service
3. An emergency change to an IT service
4. An IT service retirement

A. 2, 3 and 4 only
B. 1,2 and 4 only
C. None of the above
D. All of the above

B. 1,2 and 4 only

ITIL® Foundation – Exam Test – Q200

Which of the following are valid parts of the service portfolio?
1. Service pipeline
2. Service knowledge management system (SKMS)
3. Service catalogue

A. 1 and 2 only
B. 3 only
C. 1 and 3 only
D. All of the above

C. 1 and 3 only

ITIL® Foundation – Exam Test – Q199

Which process would you MOST expect to be involved in the management of underpinning contracts?

A. Change management
B. Service catalogue management
C. Supplier management
D. Release and deployment management

C. Supplier management

ITIL® Foundation – Exam Test – Q198

Which of the following is NOT an objective of request fulfillment?

A. To provide information to users about what services are available and how to request them
B. To update the service catalogue with services that may be requested through the service desk
C. To provide a channel for users to request and receive standard services
D. To source and deliver the components of standard services that have been requested

B. To update the service catalogue with services that may be requested through the service desk

ITIL® Foundation – Exam Test – Q197

Which of the following should be done when closing an incident?
1. Check the incident categorization and correct it if necessary
2. Check that the user is satisfied with the outcome

A. 1 only
B. Both of the above
C. 2 only
D. Neither of the above

B. Both of the above

ITIL® Foundation – Exam Test – Q196

Which of the following statements is CORRECT for every process?
1. It delivers its primary results to a customer or stakeholder
2. It defines activities that are executed by a single function

A. Both of the above
B. 1 only
C. Neither of the above
D. 2 only

B. 1 only

ITIL® Foundation – Exam Test – Q194

Which of the following activities would be performed by a process manager?
1. Monitoring and reporting on process performance
2. Identifying improvement opportunities
3. Appointing people to required roles

A. All of the above
B. 1 and 3 only
C. 1 and 2 only
D. 2 and 3 only

A. All of the above

ITIL® Foundation – Exam Test – Q193

Which process has the following objective, ‘Produce service design packages (SDPs) based on service charters and change requests’?

A. Service transition planning and support
B. Design coordination
C. Service level management
D. Change management

B. Design coordination