Which is CORRECT about change authorization?
A. A change authority is assigned each time a standard change is requested
B. Emergency changes are authorized by the technician making the change
C. Assignment of the change authority is based on the change type and model
D. The change authority will ensure changes are authorized after they are deployed
A. A change authority is assigned each time a standard change is requested
B. Emergency changes are authorized by the technician making the change
C. Assignment of the change authority is based on the change type and model
D. The change authority will ensure changes are authorized after they are deployed