ITIL Foundation V4 Exam Questions and Answers sample tests – Question053

Which describes a CORRECT approach to change authorization?


A.
Changes included in the change schedule are pre-authorized and do not need additional authorization
B. Normal changes should be assessed and authorized before they are deployed
C. Emergency changes should be authorized by as many people as possible to reduce risk
D. Normal changes are typically implemented as service requests and authorized by the service desk

Correct Answer: B